There are 2 Colossus campuses in Shelby County, Tennessee, both operating: Colossus 2 in Memphis and Colossus 1 at a Memphis address. They have 1,286 MW for their computers and 1,701 MW for the whole site. Colossus 2 should reach 1,531 MW at full size, by Feb 2027. SpaceXAI owns both and Anthropic uses both.

Checked

What does a megawatt mean?

1,286 MW is about the average use of 1.1 million homes.

1,531 MW is about the average use of 1.3 million homes.

A megawatt (MW) measures how much power a site is built to handle at one time. Think of the size of a pipe, not the water that flows through it over a year.

1,000 MW is one gigawatt (GW).

The homes number is a site running at full power all year, beside what an average US home uses in a year.

An average US home used 10,491 kWh in 2025 (EIA).

Where are Colossus 1 and 2?

Both are in Shelby County, Tennessee.

Shaded: 1 state with a Colossus campus. The dot marks the one placed at a street address. Colossus 1 is placed only to its county, so it has no dot.
  • Colossus 2Memphis, Tennessee · Listed address: 5420 Tulane Rd, Memphis, TN 38109
  • Colossus 1Shelby County, Tennessee · Listed address: 3231 Riverport Rd, Memphis, TN 38109

How big is Colossus, and how big will it get?

How to read this chart

Each bar is the power the computers are built for at the end of that year. Years after 2026 are Epoch AI's forecast.

Epoch AI, a research group, makes these estimates from satellite photos, permits and company news. They can be off by a fair amount.

Colossus 2 is the bigger one, with 946 MW for its computers now.

  • Colossus 2

    Operating

    For the computers now: 946 MW, whole site 1,276 MWWhen finished: 1,531 MW for the computers, 2,065 MW for the whole site, by Feb 2027First online: Oct 2025Chips: B200 and B300About 1,111,673 H100 equivalentsBuilding cost so far: about $35.8 billion

    H100 equivalents

    An H100 equivalent counts AI chips as if each one were an Nvidia H100, a common AI chip. It lets you compare sites that use different chips.

  • Colossus 1

    Operating

    For the computers now: 340 MW, whole site 425 MWFirst online: Aug 2024Chips: B200, H100 and H200About 275,796 H100 equivalentsBuilding cost so far: about $12.9 billion

By the end of 2027, about 1,871 MW for the computers is expected, up from 579 MW at the end of 2025.

5792025
1,2862026
1,8712027

Colossus 1Colossus 2

Megawatts (MW) for the computers at the end of each year.

Table
Site202520262027
Colossus 1340340340
Colossus 22399461,531
In all5791,2861,871

Who owns and uses Colossus?

Owners and users

An owner builds or holds a campus. A user runs its AI work there.

Users show at Epoch AI's "confident" or "likely" tag; a "speculative" one shows only as a possible user.

SpaceXAI owns both.

  • Colossus 2

    Used by Anthropic Cursor SpaceXAI

    Owner: SpaceXAI

  • Colossus 1

    Used by Anthropic

    Owner: SpaceXAI

SpaceXAI also owns xAI QTS Atlanta, in Atlanta, Georgia, with 17 MW for its computers.

Is Colossus 2 up and running?

Yes. Colossus 2 is operating. Its first computers came online in Oct 2025.

  • Colossus 2

    Operating

    Epoch AI's note, Jun 2026:

    The site is estimated to have at least ~830 MW of GPU server power, with at least "at least 220,000 additional GB300 processors and over 400 additional megawatts of compute power", corresponding to the "next phase of expansion" found in the following company S-1 filing, page 76. This estimate is backed up by our cooling and turbine based power production calculations. The cooling calculations suggest there is enough infrastructure to support ~850MW of IT Power. Similarly the energy production calculations support ~900MW of available IT Power. This gives us confidence that the proposed expansion was achieved in time. The roof for building 3 is halfway complete.
  • Colossus 1

    Operating

    Epoch AI's note, Jun 2026:

    No major changes to the data center since February. Solar panels have been placed next to the facility.

Questions about xAI Colossus

Where is Colossus 2?

Colossus 2 is in Memphis, Shelby County, Tennessee. Its listed address is 5420 Tulane Rd, Memphis, TN 38109. The campus list shows both.

Is Colossus 2 up and running?

Yes. Colossus 2 is operating, with 946 MW for its computers. It should reach 1,531 MW at full size, by Feb 2027.

What is xAI Colossus?

Colossus is the name of 2 AI campuses, in Shelby County, Tennessee. SpaceXAI owns them. Together they have 1,286 MW for their computers.

Does xAI own Colossus?

SpaceXAI owns Colossus 1 and 2. SpaceXAI also owns 1 more AI campus: xAI QTS Atlanta.

How much energy does Colossus use?

No figure for the energy used is published. The estimate is of the power the sites are built for: 1,286 MW for the computers and 1,701 MW for the whole site now. Colossus 2 should reach 2,065 MW for the whole site at full size, by Feb 2027.

Sources and updates

  • Epoch AI: "AI data centers", CC BY 4.0, retrieved November 7, 2026; changes noted.
Campus sources (11)Hide campus sources
  1. Colossus 2, WSJ profile of the Colossus data centers: wsj.com
  2. Colossus 2, Final GPU count reported by Elon Musk: x.com
  3. Colossus 2, MLGW update mentioning power requests for Colossus 2: mlgw.com
  4. Colossus 2, SpaceX-Cursor partnership to use Colossus: x.com
  5. Colossus 2, Anthropic to use Colossus 2 from June 2026: x.com
  6. Colossus 2, SpaceX S-1 filing, mentioning exact compute and power for Colossus 2: sec.gov
  7. Colossus 1, May 2025 Electricity Provider Disclosure: drive.google.com
  8. Colossus 1, July 2025 Permit for Gas Turbines: scribd.com
  9. Colossus 1, Southern Environmental Law Center Gas Permit Appeal, with additional satellite images: cdn.arstechnica.net
  10. Colossus 1, Disclosure on X (formerly Twitter) by Elon Musk of the breakdown of GPUs: archive.is
  11. Colossus 1, Anthropic announcement: anthropic.com

How CamsAhead counts cameras · Report a problem · Report a camera

Add CamsAhead to your Home Screen Open in Safari to install Drive works best from your Home Screen Open in Safari to add it to your Home Screen

It opens straight to the map.

This app’s built-in browser can’t add CamsAhead to your Home Screen.

From your Home Screen, CamsAhead opens full screen with one tap. It keeps the screen on while you drive, where your phone allows it.

  1. Tap Share
    In Safari’s toolbar, or in its ⋯ menu.
  2. Tap Share
    In your browser’s address bar or menu.
  3. Open this page in Safari
    Look for “Open in Safari” or “Open in browser” in this app’s menu, or copy the link.
  4. Copy the link, then paste it in Safari
    Or type CamsAhead.com in Safari.
  5. In Safari, tap Share, then Add to Home Screen
  6. Tap Add to Home Screen
    Scroll down the list if you don’t see it.
  7. Open the ⋮ menu
    Then tap “Add to Home screen” or “Install app”.
  8. Tap Add, then open CamsAhead from your Home Screen. Tap Install, then open CamsAhead from your Home Screen.

Don’t see Add to Home Screen? Open this page in Safari.

Or tap Share in this browser, then Add to Home Screen.

Alerts work while CamsAhead is open on screen, from the Home Screen or the browser. If the screen locks or you switch apps, they stop.

DriveBetaReport a problem