Meta's Hyperion data center in Richland Parish, Louisiana
Hyperion is Meta's AI campus in Richland Parish, Louisiana (listed address: Holly Ridge). It is not yet operating. It should first come online in Jan 2028 and reach full size that month: 1,632 MW for its computers and 2,203 MW for the whole site. That makes it Meta's largest planned AI campus.
What does a megawatt mean?
1,632 MW is about the average use of 1.4 million homes.
2,203 MW is about the average use of 1.8 million homes.
A megawatt (MW) measures how much power a site is built to handle at one time. Think of the size of a pipe, not the water that flows through it over a year.
1,000 MW is one gigawatt (GW).
The homes number is a site running at full power all year, beside what an average US home uses in a year.
An average US home used 10,491 kWh in 2025 (EIA).
Where is Hyperion?
In Richland Parish, Louisiana. Its listed address is Holly Ridge, LA 71269.
How big will Hyperion be?
How to read this chart
Each bar is the power the computers are built for at the end of that year. Years after 2026 are Epoch AI's forecast.
Epoch AI, a research group, makes these estimates from satellite photos, permits and company news. They can be off by a fair amount.
It should reach full size by Jan 2028: 1,632 MW for its computers and 2,203 MW for the whole site. That is the most planned at any Meta campus.
Chips: Rubin
Meta Hyperion
Megawatts (MW) for the computers at the end of each year.
Table
| Site | 2025 | 2026 | 2027 | 2028 |
|---|---|---|---|---|
| Meta Hyperion | – | – | – | 1,632 |
When will Hyperion open?
It should first come online in Jan 2028.
- Nov 2026Not yet operating
- Jan 2028Expected first online
Epoch AI's note, Apr 2026:
Building 1 and 2 roof is finished and cooling is at an advanced stage of installation. Building 3 and 6 roof and cooling in progress.
Who is building and powering it?
Meta owns it and will use it. Mortenson is the builder and Entergy is the power company.
Used by Meta
Owner: Meta · Project: Hyperion
Built by: Mortenson
Power company: Entergy
Questions about Hyperion
Where is Meta's Hyperion data center?
Hyperion is in Richland Parish, Louisiana. Its listed address is Holly Ridge, LA 71269.
How big is Hyperion?
It should reach full size by Jan 2028: 1,632 MW for its computers and 2,203 MW for the whole site. It is not yet operating.
When will Hyperion open?
It should first come online in Jan 2028.
Who is building Hyperion?
Mortenson is the builder. Meta owns it. Entergy is the power company.
Is Hyperion Meta's largest data center?
Not yet: it is not yet operating. Among Meta's running campuses, Prometheus has the most, with 471 MW for its computers. Hyperion has the most planned: 1,632 MW for its computers at full size, by Jan 2028. Meta's AI data centers lists each one.
Sources and updates
- Epoch AI: "AI data centers", CC BY 4.0, retrieved November 7, 2026; changes noted.
Campus sources (4)Hide campus sources
- Meta Hyperion, Data center profile by Meta: datacenters.atmeta.com
- Meta Hyperion, Entergy's application for generation and transmission resources: drive.google.com
- Meta Hyperion, MISO update with 1.8 GW substation plan: drive.google.com
- Meta Hyperion, S&P Global ratings research with 2.064 GW campus details: spglobal.com